- The prototype needs to be usable from the user point of view
- The data and analytics behind the prototype should be validated; is the data of the right sort? Does the competence profile provide experienced value to the learner? (Both in independent use or in guidance situations)
Phase | Planned start date (MM/YYYY) | Planned end date (MM/YYYY) |
Specification | 01/2019 | continuous |
User interface design | 02/2019 |
08/2019 | ||
Implementation | 02/2019 | 05/2019 |
Finishing and refining | 06/2019 | 08/2019 |
Testing | 04/2019 | 09/2019 |
Piloting | 06/2019 | 11/2019 |
The working method follows a ”Scrumban-hybrid” approach, in which the objective state is approached one functionality at a time.
...
The creation of the prototype is afforded ca. 250 person-days (PDs). This enables the resourcing illustrated in the table below. One month is ca. 22 PDs.
Month | Developers | UI designers |
02/2019 | 1 | 1 |
03/2019 | 1,5 | 1 |
04/2019 |
2
1,8 | 0,4 |
05/2019 |
2
1,8 | 0,4 |
06/2019 | 1,8 |
0,4 | |
08/2019 | 1 |
0,4 |
Additionally service designer affordances for ~8 PDs can be included.
...