Del.No WPNameTypeResponsible

Planned Delivery Date

Status

Approved by

Approval date

Comments 
01WP1Standard management report Q1ReportAntti Laitinen2018.02.28Ready - report sent to project officerProject management committee + steering committee

14.6.2018

link to steering committee memo 14.6


02WP1 

Standard management report Q2

ReportAntti Laitinen2018.08.30Ready - report sent to project officerProject management committeeapproved by e-mail between 17.8.-31.8.
03 WP1 

Standard management report Q3

ReportAntti Laitinen2019.02.28
Project management committee

04 WP1 

Standard management report Q4

ReportAntti Laitinen2019.08.30
Project management committee

05 WP1 

Standard progress report P1

ReportAntti Laitinen2018.05.30Ready - report sent to project officerProject management committee + steering committee

14.6.2018

link to steering committee memo 14.6.



06 WP1 

Standard progress report P2

ReportAntti Laitinen2018.11.30
Project management committee17.1.2019 (included in periodic report)
07 WP1 

Standard progress report P3

ReportAntti Laitinen2019.05.30
Project management committee

08 WP1 

Project Roadmap

DocumentAntti Laitinen2019.11.30Living document in Eduuni wiki


09 WP1 

Project management and steering groups meetings

Event, DocumentAntti Laitinen2019.11.30



10 WP1 

Midterm report

ReportAntti Laitinen2018.11.30
Project management committee17.1.2019 (periodic report)
11 WP1 

Final report

= Periodic report + final report

ReportAntti Laitinen

2019.11.30 (draft)

Final version January 9th


Project management committee

12 WP1 

Eduuni wiki webpage

WebsiteAntti Laitinen2017.12.30Ready - report sent to project officerProject management committee19.3.2018
13 WP1 

Eduuni workspace

WebsiteAntti Laitinen2017.12.30Ready - report sent to project officerProject management committee19.3.2018
14 WP1 

Risk Management Plan

D14 re-submitted version

DocumentAntti Laitinen2018.2.28Re-submitted  March 14thProject management committee + steering committee

14.6.2018

link to steering committee memo 14.6.


15 WP2

Desk research


D15 re-submitted version

DocumentAnnica Moore2018.02.28


Re-submitted  March 14th


Project management committee

Done for Finland and Netherlands,

Possibly to be expanded for other European partners during the project implementation

16 WP2

Kick-off seminar and workshops in cooperation with WP5

EventAnnica Moore2018.04.30Ready - report sent to project officerProject management committee

17 WP2

Task-force and WP2 meetings and meeting notes

EventAnnica Moore2018.04.30Ready - report sent to project officerProject management committee
 The "task-force" will keep meeting during the whole development phase
18 WP2

Detailed description of the user scenarios with guidelines and advice for developers in WP3


D18 re-submitted version

DocumentAnnica Moore2018.05.30Re-submitted  March 14thProject management committee
User needs are continuously tested with selected key target groups affecting and changing user scenarios
19 WP2

Mid-term review seminar in cooperation with WP5

EventAnnica Moore2018.11.30Ready - report sent to project officerProject management committee

20 WP2

Running prototypes in cooperation with WP3


PrototypeAnnica Moore2019.05.30
Project management committee

21 WP2

Feedback and specifications to user scenarios

PrototypeAnnica Moore2019.05.30
Project management committee
User needs are continuously tested with selected key target groups
22 WP2

Final seminar in cooperation with WP4 and WP5

EventAnnica Moore

Updated delviery date 2019.10.31


Ready - report sent to project officerProject management committee

23 WP2

Sustainability Plan

DocumentAnnica Moore2019.10.30Ready - report sent to project officerProject management committee

24 WP3

Open source code for all components, including example code

DocumentAnnica Moore2019.05.30
Project management committee

25 WP3

Technical documentation, including glossary, model and architecture

DocumentAnnica Moore2019.05.30
Project management committee

26 WP3

Three prototypes

PrototypeAnnica Moore2019.05.30
Project management committee

27 WP4

Pilot deployment of the architecture

PilotTarja Puura2019.09.30Ready - report sent to project officerProject management committee27.9.2019
28 WP4

Pilot deployment of analytics prototype

PilotTarja Puura2019.09.30Ready - report sent to project officerProject management committee27.9.2019
29 WP4

Pilot deployment of learner plan prototype

PilotTarja Puura2019.09.30Ready - report sent to project officerProject management committee27.9.2019
30 WP4

Report on pilot deployment of the architecture

PilotTarja Puura2019.10.31Ready - report sent to project officerProject management committee24.10.2019
31 WP4

Report on pilot deployment of analytics

PilotTarja Puura2019.10.31Ready - report sent to project officerProject management committee 24.10.2019
32 WP4

Report on pilot deployment of learner plan prototype

PilotTarja Puura2019.10.30Ready - report sent to project officerProject management committee24.10.2019
33 WP4

Impact evaluation study that will provide in-depth evaluation of effectiveness and usability of the produced digital solutions in cooperation with WP1

DocumentTarja Puura2019.11.30
Project management committee18.11.2019FINEEC external evaluation report
34 WP5

Dissemination and Communication Plan

DocumentMonique Leegte2018.02.28Ready - report sent to project officerProject management committee

35 WP5

Stakeholder management plan


D35 re-submitted version

Document Monique Leegte 2018.02.28 Re-submitted  March 14thProject management committee 

36  WP5

Project identity

OtherPeter Heeling2018.02.28Ready - report sent to project officerProject management committee

37  WP5

Project Website

WebsitePeter Heeling2018.02.28Ready - report sent to project officerProject management committee

38  WP5

Presentations and Publications

OtherVera Wemer2019.11.30New and all the publications can be found on the projectwebsiteProject management committee

39  WP5

Targeted workshops and seminars in cooperation with WP2


EventVera Wemer2018.05.30-2019.11.30
Project management committee