Status | Mini-Milestone | Date | Comments | |
---|---|---|---|---|
DelayedFinished | Denmark's NCP in production | 1.10.2016 | February | In production 28.5.2017 |
Finished | Italy's NCP/SMP in production | 1.10.2016 | NCP in production. SMP still in production in developmentApril 2017 | |
FinishedSecond version ready | Introduction for new parties: EMREX for dummies | 15.2.2017 | Final version for publishing on emrex.eu ready in April 2017 | |
Quality assurance of open source code | 1.8.2017 | |||
Define Code maintenance process (common code) | 1.11.2017 | |||
Agree on license model for common code | 1.11.2017 | |||
Risk analysis for the EMREX network | 1.10.2017 | See Risk analysis for EMREX (mostly technical issues). Need a couple of meetings for this (use a couple of hours of PG meetings?) | ||
Standard architecture drawing for EMREX | 15.9.2017 | Togaf-based - for the standardisation document | ||
Implementation of ELMO 2.0/ELMO 1.2 in all NCPs | 1.11.2017 | Dependent on WP6 - updated schema |
Activities in 2017
The project deliverables for WP3 was mainly completed in 2015 and 2016. A few smaller activities has been identified for 2017, defined in the mini milestone list above. In addition, WP3 will provide help for new EMREX parties during 2017 (DUO, Sigma, others?)
...
NCP Development Milestones | NO | SE | DK | FI | IT | PL | ||
---|---|---|---|---|---|---|---|---|
Retrieving of results from data source | 01.09.2015 | 1.9.2015 | 15.08.2016 | 20.11.2015 | 07/01/2016 | 12.10.2015 | ||
User interface (course selection) | 15.09.2015 | 15.9.2015 | 01.12.2016 | 20.11.2015 | 07/01/2016 | 12.10.2015 | ||
Generate PDF to enclose in the ELMO document | 02.11.2015 | 30.11.2015 | 01.12.2016 | 20.11.2015 | 07/01/2016 | 1.09.2016 | ||
Generate and sign the ELMO document | 25.09.2015 | 13.11.2015 | 01.12.2016 | 3.11.2015 | 08/01/2016 | 12.10.2015 | ||
Make the ELMO document compatible with the EMREX 1.0.0 Schema | 07.12.2015 | 23 | 01. | 0105. | 20162017 | 08/01/2016 | 7.12.2015 | |
Return data to SMP-client | 25.09.2015 | 25.9.2015 | 01.12.2016 | 3.11.2015 | 08/01/2016 | 12.10.2015 | ||
Logging | 26.10.2015 | 22.1.2016 | 01.12.2016 | 17.11.2015 | 08/01/2016 | 15.11.2015 | ||
Infrastructure for test environment (database, servers, certificates) | 25.09.2015 | 13.11.2015 | 1501. | 0105.2017 | 1.9.2015 | 08/02/2016 | 15.12.2015 | |
Get certificate for test NCP, populate EMREG-test with address and certificate for NCP | 09.10.2015 | 13.11.2015 | 01.01.2017 | ?? | 08/02/2016 | 1.09.2016 | ||
Get certificate for production NCP, populate EMREG-prod with address and certificate for NCP | 16.10.2015 | 13.11.2015 | 1901. | 0104.2017 | 15.5.2016 | 08/02/2016 | 1.09.2016 | |
NCP ready for user test | 15.12.2015 | 30.11.2015 | 2301. | 0105. | 20162017 | 17.11.2015 | 22/02/2016 | 15.12.2015 |
NCP ready for field trial (latest) | 15.01.2016 | 01.03.2016 | 0829. | 0205. | 20162017 | 24.8.2016 | June 2016 | 1.09.2016 |
...
EMREX Client Development Milestones | NO | SE | DK | FI | IT | PL |
---|---|---|---|---|---|---|
Authentication | N/A | 26.2.2016 | N/A | 6.10.2015 | 14.01.2016 | 30.09.2016 |
SMP set up | 09.10.2015 | 26.2.2016 | N/A | N/A | 22.01.2016 | 30.09.2016 |
User interface | 02.10.2015 | 26.2.2016 | N/A | 3.11.2015 | 22.01.2016 | 15.10.2016 |
Verify data from NCP | 16.10.2015 | 26.2.2016 | N/A | 3.11.2015 | end of february 2016 | 15.10.2016 |
Store collected data | 16.10.2015 | 11.3.2016 | N/A | 3.11.2015 | July/August 2016 | 30.10.2016 |
Redirect customer for field trial questionaire | 02.11.2015 | 26.2.2016 | N/A | 17.11.2015 | July/August 2016 | 4.11.2016 |
Log entries | 15.01.2016 | N/A | 17.11.2015 | July/August 2016 | 4.11.2016 | |
SMP-client implemented in test environment | 20.10.2015 | 1.2.2016 | N/A | 17.11.2015 | January 2017 | 30.10.2016 |
SMP-client ready for user test | 15.12.2015 | 1.2.2016 | N/A | 17.11.2015 | January 2017 | 30.10.2016 |
SMP-client ready for field trial (in production environment) | 15.01.2016 | 26.2.2016 | N/A | 15.4.2016 | FebruaryApril 2017 | January 2017 |
SMP Common code
...