This timeline picture and the table after it will help the steering committee to check when the deliverables should be reported and when it´s expected to get feedback from the steering committee members concerning the deliverables. The draft versions of the deliverable report can be found here in Eduuni wiki in Deliverables.



Steering committee meeting

Deliverable +

status (green = deliverable is ready, yellow = ongoing, red = not yet started)


Draft version in Eduuni wikiSteering committee comments by e-mail
April 9th 2018

Del.No 12 Eduuni wiki webpage

Del.No 13 Eduuni workspace

Del.No 34 Dissemination and Communication Plan

Del.No 35 Stakeholder Management plan

Del.No 36 Project Identity

Del.No 37 Project website



June 14th 2018

Del.No 1 Standard management report Q1

Del.No 5 Standard progress report P1

Del.No 14 Risk Management Plan

Del.No 15 Desk research

Del.No 16 Kick-off seminar and workshops in cooperation with WP5

Del.No 17 Task-force and WP2 meetings and meeting notes

Del.No 18 Detailed description of the user scenarios with guidelines and advice for developers in WP3





Del.No 2 Standard management report Q2 17.8.2018 17.8.-30.8.




October 18th 2018



Del.No 6 Standard progress report P2 16.11.2018 16.11.-29.11.2018

Del.No 19 Midterm review seminar in cooperation with WP5 16.11.2018 16.11.-29.11.2018

Del.No 10 Midterm report    16.11.2018 16.11.-29.11.2018
 February 6th 2019



Del.No 3 Standard management report Q3 14.2.2019 14.2.-27.2.2019




March 29th 2019



Del.No 7 Standard progress report P3 17.5.201917.5.-30.5.2019 

Del.No 20 Running prototypes in cooperation with WP3  17.5.201917.5.-30.5.2019 

Del.No 21 Feedback and specifications to user scenarios 17.5.201917.5.-30.5.2019 

Del.No 24 Open source code for all components, including example code 17.5.201917.5.-30.5.2019 

Del.No 25 Technical documentation, including glossary, model and architecture 17.5.201917.5.-30.5.2019 

Del.No 26 Three prototypes 17.5.201917.5.-30.5.2019 
May 25th 2019



Del.No 4 Standard management report Q4 16.8.201916.8.-29.8.2019
 August 26th 2019



Del.No 27 Pilot deployment of the architecture  26.9.2019

Del.No 28 Pilot deployment of the analytics prototype  26.9.2019

Del.No 29 Pilot deployment of the learner plan prototype 26.9.2019
 September 27th 2019



Del.No 30 Report on pilot deployment of the architecture 23.10.2019

Del.No 31 Report on pilot deployment of the analytics 23.10.2019

Del.No 32 Report on pilot deployment of the learner plan 23.10.2019

Del.No 23 Sustainability Plan   23.10.2019 

Del.No 22 Final seminar in cooperation with WP4 and WP5 23.10.2019
 October 24th 2019



Del.No 33 Impact evaluation study that will proved in-depth evaluation of effectiveness and usability of the produced digital solutions in cooperation with WP1 15.11.2019 

Del.No 38 Presentations and Publications 

15.11.2019 

Del.No 39 Targeted workshops and seminars in cooperation with WP2 15.11.2019

Del.No 8 Project Roadmap 15.11.2019

Del.No 9 Project management and steering group meetings15.11.2019

Del.No 11 Final report (Periodic report + final report - final version ready two weeks before the  final review)15.11.2019

External evaluation fact check November 15th-19th (to be linked when FINEEC deliveres it)15.-19.11. 
 November 18th 2019



 Del.No 11 Final report (Periodic report + final report ready two weeks before the  final review)

January x?


January 23rd 2020 final review