Current risks management for 2017-2019

The following current risks have been identified to require intervention


P = Probability Low (1) - Medium (2) - High (3)

I = Impact Insigificant (1) - Low (2) - Medium (3) - High (4) - Critical (5)


                                                                                                                                                                                                                                                                                                                                   

  

 ID

  
  

Issue

  
  

 P

  
  

  
  

How to    prevent this risk to happen? Actions to be taken when such risk arise?

  
  

Responsible

  
 18Prototype development and stakeholder feedback 



  

17

  
  

Framework    architecture evaluation is not progressing as planned with the existing    partners

  
  

1

  
  

3

  
  

Urgent reaction    by project management committee and updating the timetables

  

-           Road map + KPI monitoring

  
  

CSC, EDUFI, Gradia

  
  

17a

  
  

Consortium is    not able to organise the planned workshops/evaluation events

  
  

1

  
  

4

  
  

Re-organising    the workshop timetables

  
  

CSC, EDUFI, Gradia

  
  

17b

  
  

Documentation    of the evaluation meetings is not sufficient enough

  
  

1

  
  

3

  
  

Preparing the    documentation and allocating extra time to this if needed

  
  

CSC, EDUFI, Gradia

  
  

17c

  
  

No other    interested partners joining the pilot deployment of the architecture

  
  

2

  
  

2

  
  

Consortium    will continue actively (existing networks, communication calendar) seeking    interested partners – otherwise focusing on the existing networks which will    fullfil what is promised in Annex I

  
  

CSC, EDUFI,    DUO, Gradia

  
  

16

  
  

Analytics    development is not progressing as planned

  
  

2

  
  

3

  
  

Active    reaction by project management committee and re-organising the task force

  

-           Road map + KPI monitoring

  
  

UOulu

  
  

16a

  
  

Technical    development of the analytics facing trouble

  
  

2

  
  

5

  
  

Active    collaboration from partners with the subcontractor

  
  

Uoulu, EDUFI

  
  

16b

  
  

Analytics is    developed separately – not in close relation to WP3

  
  

2

  
  

3

  
  

Close    collaboration with EDUFI and Uoulu

  

Project    management will react if needed

  
  

Uoulu, EDUFI

  
  

16c

  
  

Deployment of    the analytics facing trouble

  
  

2

  
  

3

  
  

Re-planning    the deployment timetable

  
  

Uoulu, Gradia

  
  

15

  
  

Learner plan    and its modelues development is not progressing as planned

  
  

2

  
  

5

  
  

Active    reaction and re-organising the work package

  

-           Road map + KPI monitoring

  
  

EDUFI

  
  

15a

  
  

Technical    development of the learner plan facing trouble

  
  

2

  
  

5

  
  

Active    collaboration with the subcontractor

  
  

EDUFI

  
  

15b

  
  

Deployment of    the learner plan facing trouble

  
  

2

  
  

3

  
  

Re-planning    the deployment timetable

  
  

EDUFI, Gradia

  
  

15c

  
  

The    consortium is not able to deliver the expected additional documents in M18    (see the review feedback)

  
  

1

  
  

5

  
  

These    documents must be delivered in time – no choice

  
  

EDUFI

  
  

14

  
  

Europass case    study development facing difficulties

  
  

2

  
  

2

  
  

Finding ways    to manage with the difficulties – focusing on the other parts of the project    if the collaboration seems to be impossible for some reason

  

-           Road map + KPI monitoring

  
  

EDUFI, DUO

  
  

14a

  
  

Difficulties    organising the workshop(s) with the Europass network

  
  

1

  
  

4

  
  

Re-organising    the workshop timetables

  
  

DUO

  
  

14b

  
  

Documenting    the case study facing problems

  
  

1

  
  

3

  
  

Allocating    extra time for documentation work

  
  

EDUFI, DUO

  
  

13

  
  

Engaging    communication on the project results is not good enough

  
  

1

  
  

3

  
  

Involving    more people working on the communications

  

-           Road map + KPI monitoring

  
  

DUO, CSC, EDUFI

  
  

13a

  
  

Not enough    resources staff involved to communications

  
  

1

  
  

3

  
  

Re-organise    the staffing internally by project management committee - steering committee    supporting

  
  

DUO, CSC, EDUFI

  

13b

The Consortium   is not able to collect measurable data from the communications

1

4

Pre-planning   of the communications

DUO, CSC, EDUFI

12

Quality of the   deliverable reports is not good enough

1

4

Separate   deliverable report preparing meetings organised – project management   responsible – detailed timetable

CSC

11

Impact   evaluation study is not been able to organise as planned

1

3

Consortium   will organise the impact evaluation study internally

Gradia

10

Finding suitable international piloting   partners in other EU countries

2

3

The Consortium   should turn on to existing partnerships of partner organisations – steering   committee supporting

Gradia

9

Staffing - Project team also involved in   other projects

3

4

Make sure that project team staff has enough   resources and time to contribute to Compleap and that simultaneous projects   are synergetic


All partners

8

Difficulties with the portability of prototypes:   extra work needs to be done to implement the prototypes (for example national   databases)

1

3

Learner plan   modules  were chosen to avoid this risk

EDUFI

7

The outcome   of  the project does not meet the objectives and requirements

1

4

The chosen   agile  project method will be strictly used to ensure continuous   adjustment of the   project work towards the agreed steps and goals

All partners

6

There     is insufficient key professional resources available for this project

2

4

The workload   of the persons assigned to the  project is being monitored to ensure   sufficient allocation for the project.   For every key role in the   project there will be a responsible person and a   substitute person   nominated.

All partners

5

Deliverables   developed are not available in due time of the   project.

2

4

Periodic     progress reviews allow decision to lower level of ambition and reduce     likelihood of this becoming an issue.


CSC

4

Failure to     choose the right

technologies

2

4

Select   technologies   on basis of community interfaces and on international   standards. Support multiple   interfaces and/or adapt community services   to comply with international   standards.

EDUFI

3

Failure to     engage effectively with stakeholders

(e.g.,     weak attendance to shared seminars)

2

3

Project     already has a interested stakeholders on board. In addition, representatives     in all work packages act as ambassadors.

All partners

2

Failure to     define the right architecture incl. organisational and business   model  required to ensure a sustainable uptake.

2

4

Start   work  on this early and allow for several iterations. Involve   stakeholders in the discussion. Learn from the experiences of similar   initiatives such as EMREX.

CSC, EDUFI

1

Lack   of response and cooperation from one individual partner preventing   timely delivery of project results, including deliverables.

1

4

Early     intervention of Project Coordinator, leading to escalation to Project     Management Committee and ultimately, to Steering Group, and decision over     corrective actions, such as reassessing responsibilities and tasks   among the consortium.

CSC

Please see Compleap's approach on risk management on Compleap's Risk management plan