Both of these documents should be delivered to project officer 60 days after the end of Month 12 (November 2018). Project coordinator will inform the Consorium of this reporting and gather all the information TIMETABLE for financial and technical report MID-TERM REVIEW IN LUXEMBOURG Mid-term review is organized in European Comission in Luxembourg. Each wp leader should take part this meeting and prepare to present what has been done in the project so far. Review is based on the deliverable report that have been sent to the project officer by the time.
Mid-term reporting includes two kinds of reports:What? When? Status Financial + technical template updated and sent to coordinator by 20th of December Coordinator makes summary 1st week of January To be sent to steering committe to be approved 7th of January Approval (by e-mail) and updates by 17th January To be sent to project officer and reviewers - material to be used in the review January 30th-31st January 17th