Mid-term reporting includes two kinds of reports: - financial report (draft version of the template), which is a summary of financial side of the project during the first year
- technical report (draft version of the template), which is a summary of progress made during the first project year
Both of these documents should be delivered to project officer 60 days after the end of Month 12 (November 2018).
Project coordinator will inform the Consorium of this reporting and gather all the information - each partner must deliver updated financial report template as instructed
- The coordinator will take care of the technical report
TIMETABLE for financial and technical report
What? | When? | Status |
---|
Financial + technical template updated and sent to coordinator | by 20th of December | | Coordinator makes summary | 1st week of January | | To be sent to steering committe to be approved | 7th of January | | Approval (by e-mail) and updates | by 17th January | | To be sent to project officer and reviewers - material to be used in the review January 30th-31st | January 17th | |
MID-TERM REVIEW IN LUXEMBOURG
Mid-term review is organized in European Comission in Luxembourg. Each wp leader should take part this meeting and prepare to present what has been done in the project so far. Review is based on the deliverable report that have been sent to the project officer by the time. |