 M15 ( February 2019) M16 (March 2019)M17 (4/2019)M18 (5/2019)M19 (6/2019) M20 (7/2019)M21 (8/2019) M22 (9/2019) M23 (10/2019) M24 (11/2019) 
WP1: Project management (CSC) Del 3.Standard management report Q3         
    Del 7. Standard progress report P3      
          Del 9. Project management and steering group meetings 
          Del 11: Final report
WP2: Requirements and architecture design (EDUFI)Del 15. Desk research (re-submitted)Deliverable 15: Desk research - re-submitted by March 14th

      
 Del 18. Detailed description of the user scenarios (re-submitted)  Deliverable 18: DEtailed description of the user scenarios - re-submitted by March 14th         
    Del 20. Running prototypes in cooperation with WP3      
    Del 21. Feedback and specifications to user scenarios      
      Del 22. Final seminar in cooperation with WP 4 and WP5 (must be re-scheduled because of summer)     
         Del 23. Sustainability plan (Document) 
TF Learning analytics  (UOulu)          
WP3: Prototype development (EDUFI)

Provide additional documents concerning the Development of the Beta prototype (WP3) - by M18:


(Developing and releasing the initial version of the Beta prototype (Beta part 1) by Month 18 and the full Beta version (Beta part 2) by Month 22);

- Detailing the criteria adopted for selecting key functionalities to be developed in the Beta version;

- Developing a detailed plan for the piloting of the Beta prototype (WP3);

- Developing a detailed deployment plan of the Beta prototype (WP4).



Del 24 Open source code for all components including example code      




Del 25. Technical documentation, including glossary, model and architecture       
     Del 26. Three prototypes       
WP4: Deployment and (Gradia)evaluation   Del 27.Pilot deployment of the architecture (Pilot)  
   Del 28. Pilot deployment of the learning analytics prototype (Pilot)  
   Del 29. Pilot deployment of the learner plan prototype (Pilot)   
      Del 33 Impact evaluation study in cooperation with WP1 (Document) 
WP5: Dissemination and (DUO)communication Del 38. Presentations and publications (Other) 
 Del 39. Targeted workshops and seminars in cooperations with WP2 (Event) 
 Del 35. Stakeholder management plan (re-submitted) (Document) Deliverable 35: Stakeholder Management plan - re-submitted by March 14th         
Main goals and project resultsResponsible / Work package Identified risks 

Key Performance Indicators (KPI) - measurements 

  • Kuukausittainen työmäärä
  • kuukausittaiset talousluvut
  • tarkemmat milestonet
Definition of conceptsDone so farTo be doneDeploymentCommunication and dissemination of activitiesDeliverables across timelineEvaluation

Framework architecture

Main architecture aspects and system requirements

Ecosystem and modules user scenarios

WP2

  • EDUFI: Sami, Annica
  • CSC: Ari, Antti

Deployment

WP4

  • Gradia: Tarja
  • CSC:
    Ari, Antti, Anu
  • EDUFI
    Sami, Topias

 

  

T1.1 Framework architecture design

T1.2: Personal learner plan and user scenarios

User processes

T1.3: Learning environments and analytics

Information Architecture

Information Systems Architecture (Application Architecture)

System requirements

 

M17-M22

April-September

Link to detailed plan

M17-M22

April-September

Link to detailed plan

Link to communication calendar and stakeholder management

Del 27 Pilot deployment of the architecture 

Del 30 Report on pilot deployent of the architecture

Impact evaluation study 

Analytics prototype

  • competence visualizations
    • natural language processing, Koski-tiedot muutetaan kansankielisiksi osaamisiksi, jotka käyttäjä pääsee valitsemaan osaksi profiiliaan. Tuotetaan algoritmi ja sen yksinkertaisin mahdollinen toteutus

WP2 TF-LEA

  • UOulu: Hanni, Egle,
  • EDUFI:  

Deployment

WP4

  • Gradia: Tarja
  • UOulu: Hanni, Egle, Antti K.
  • CSC:  Antti, Anu
  • EDUFI  Topias

 

  

Competence visualisation based on desk research (literature) and reference group generated ideas in workshops

Definition of data sources and Integration of in and outputs to the competence mapping

Educations recommendation desk research (literature)

Progression plan for the CompLeap prototype

National deployment

(Finland - all prototypes)

Link to communication calendar and stakeholder management

 Deliverable 28 Pilot deployment of analytics prototype

Learner plan prototype incl 3 modules

  • Initial functionalities incl. interface, content and associated services
  • Reference group review of functionalities
  • Finalized definition of functionalities incl. interface, content and associated services

 WP3

  • EDUFI: Annica, Marcus, Outi
  • Reaktor 

Deployment

WP4

  • Gradia: Tarja
  • EDUFI: Annica, Topias
  • UOulu:
  • CSC:  Antti, Anu

 

  

Three prototypes defined as:

  • local service integrations - KOSKI, Diploma register (past)

  • competence profile (present)

  • suggestions - education opportunities (future)

Developing and releasing the initial version of the Beta prototype (Beta part 1) by Month 18 and the full Beta version (Beta part 2) by Month 22);

Progression plan for the CompLeap prototype

Implemented by the 30th of May 2019

Competence Profile

  • The learner’s competencies are shown to the learner based on their KOSKI-data and data from eCurriculum
  • The learner can provide prior and future interests, which are shown as competencies

Recommended educational offer

  • based on competencies
  • based on interests

Recommendation system needs for analytics and algorithm availability

Developing and releasing the initial version of the Beta prototype (Beta part 1) by Month 18 and the full Beta version (Beta part 2) by Month 22);

Finalised functionalities by 30th of August

The user piloting of the prototypes begins in May. Improvements to usability and tweaks based on feedback received in piloting are implemented by the 30th of August. Additionally, the possibility for the learner to include their Europass as well as Open Badges will be implemented in this stage.

Online Demo-sessions to support prototype development

will be held every two weeks from March 2019.

National deployment

(Finland - all prototypes)

International deployment

(Netherlands, Germany + possible other countries)

 

Link to communication calendar and stakeholder management

Deliverable 26 Three prototypes (modules)

Deliverable 29 Pilot deployment of learner plan prototype

Deliverable 18: DEtailed description of the user scenarios - re-submitted by March 14th